Excavation Work

Trenches kill people who underestimated soil. Plan services first, classify the soil, choose the right protection, keep plant out of the zone of influence.

Quick Take
  • > 1.5 m trench/shaft = HRCW; SWMS required before work starts.
  • Dial Before You Dig + pothole if location uncertain.
  • Spoil ≥ 1 m from edge; ladder within 7.5 m of every worker.
  • "Hard compact" soil is the deceptive one — it looks safe and fails suddenly.
  • No plant in the zone of influence unless shoring designed for it.

1. Who's responsible

PCBU doing the excavation — primary duty (s.19): plan, prepare SWMS, brief workers, supervise.

Principal Contractor (project ≥ $250k) — Reg 304: obtain underground essential services info before excavation; provide it to all excavating PCBUs; verify they understand it.

Designer — flag deep services, adjacent foundations, soil conditions in the safety report (Reg 295).

Worker — comply with SWMS; report changes (water, cracks, vibration, weather effects).

2. When this code applies

Definition: work to make, fill or partly fill excavations — trenches, shafts, tunnels. Excludes mines, bores under water law, interment trenches.

HRCW trigger (Reg 291): excavation depth > 1.5 m in shaft or trench, or any tunnel work. SWMS mandatory.

Excavation work is construction work — all construction duties apply (white card, induction, WHS Management Plan if PC project).

3. Pre-excavation planning

Underground services

  • Dial Before You Dig (1100 / dialbeforeyoudig.com.au) before any excavation.
  • Pothole with hand tools or vacuum excavation if cable/pipe location uncertain — confirm position before plant work.
  • Electromagnetic locators / GPR acceptable if operators competent.
  • Have a competent electrician on site for mechanical work near power.

Soil classification (by competent person)

TypeBehaviourProtection
Hard compactLooks safe; cracks suddenly under moisture loss / water ingress / vibration.Benching, battering, or shoring depending on depth.
Crack-prone (clay seams, shale)Dries and shrinks; fails under stress, vibration, load.Benching < 45° unless engineer-designed; shoring often required.
Loose / running (sand, gravel, silt)No cohesion. Obvious risk.Pre-installed sheet piling / closed sheeting / trench shields. Battering alone insufficient.
Groundwater-affectedBoils, undermining, pressure.Shoring + dewatering (pumps, sumps).

Site context

  • Adjacent structures — consult designer / geotechnical engineer; document existing basements.
  • Traffic / plant loads — establish the zone of influence: the soil volume affected by external loads. No plant or materials inside it unless shoring is designed for that load.
  • Weather forecast — collapse risk rises sharply with rain.

SWMS development

  • Identify hazards, hierarchy of controls, implementation, monitoring, review.
  • Include rescue plan for collapse.
  • Consult workers.

4. How trenches actually fail

![[excavation_work_img001.jpg|520]] Figure 1 — Trench collapse mechanics. Tension cracks form behind the face; a wedge slips along a curved plane; a worker is buried in seconds. A cubic metre of saturated soil weighs ~1.5 t — enough to crush.

5. Zone of influence — keep plant clear

![[excavation_work_img002.jpg|520]] Figure 2 — Zone of influence with two shoring designs: shoring for face loads only (left) vs. shoring designed for vehicle loads (right). The boundary moves with depth and soil type.

  • No plant, materials or stockpiles inside the zone unless shoring is engineer-designed for that load.
  • Use wheel stoppers / barriers — solid enough to stop a fully laden machine.
  • If plant must operate near the edge: geotechnical engineer certifies ground support for specific load magnitudes.

6. Shoring methods

Pick by depth, soil and access. Hierarchy by safety of installation:

Benching

![[excavation_work_img003.jpg|520]] Figure 3 — Benching: stepped reduction of vertical face. Suits stable rock / stiff clay / dry ground. Bench width ≥ 1000 mm; sloped to drain. Cut from bottom up.

Battering

![[excavation_work_img004.jpg|520]] Figure 4 — Battering: sloped face. Angle < 45° unless engineer-designed. Suits granular soil, weathered rock, variable conditions. Often combined with benching.

Hydraulic shoring

![[excavation_work_img005.jpg|520]] Figure 5 — Hydraulic shoring with jacks and struts. Designed by competent person for expected ground pressure. Inspect hoses/rams frequently — bent rams, abrasion, fatigue are common.

Timber soldier sets

![[excavation_work_img006.jpg|520]] Figure 6 — Timber soldier sets. Soldiers (≥ 150 × 38 mm) at max 1.5 m centres. Toms (≥ 150 × 38 mm) at max 750 mm vertical, top tom projecting ≥ 300 mm above trench. Stable soils only — open sets don't fully support the face.

Sheet piling, trench sheeting, closed sheeting, ground anchors

  • Steel sheet piling — major excavations, close to buildings, loose sand. Driven before excavation; supported by walings + jacks or tie-back anchors.
  • Trench sheeting — lightweight; pneumatically driven; toms/wallings as work proceeds. High manual-handling/laceration risk during driving; control noise.
  • Closed sheeting — continuous timber/metal planks for full face support; required where slippage between supports is a risk.
  • Ground anchors (tie-backs) — resin/grout plugs in soil behind sheet piling, designed by geotechnical engineer.

Trench shields / boxes

![[excavation_work_img007.jpg|520]] Figure 7 — Typical trench shield. Portable steel cage that protects workers from collapse; not a substitute for shoring of the face itself in unstable ground.

7. Spoil management

  • 1 m clear of trench top (typical).
  • Slope spoil away from edge to drain water away from face.
  • High-side placement risks overload — prefer low-slope side; reduces effective excavation depth.
  • "Angle of repose" for unsupported face fails — different soils slip at different slopes; never assume the natural pile slope is safe for a cut face.

8. Access & egress

  • Ladder within 7.5 m of every worker in any excavation > 1 m.
  • Ladder secured (tied/braced/weighted), full-width, extends ≥ 1 m above the step-off, positioned to prevent slipping.
  • Ramps/steps: even, non-slip, adequate gradient; barriers/guards where used.
  • Multiple emergency egress routes.

9. Atmospheric & confined-space considerations

  • Deep trenches, tunnels, work near sewers/gas/fuel/contamination → potential for confined-space classification.
  • Hazards: CO from engines, methane, H₂S, O₂ depletion, explosive atmospheres.
  • Controls: mechanical ventilation (engineered), continuous gas monitoring, buddy/standby system, breathing apparatus where atmosphere unmanageable, prohibited combustion plant in occupied trenches.
  • See §08 [[confined_spaces]] (Phase 3).

10. Hazard summary

HazardPrimary controlSecondary
CollapseEngineer-designed shoring; benching/batteringDaily inspection (post-rain, post-vibration)
Falls into excavationGuardrails, covers, shields, perimeter barriersRescue procedures
Water inrushDewatering pumps + sumps; drainage designSlope to direct water away
AtmosphereMechanical ventilation; gas monitoringRescue prep, BA
Plant collisionComms, blind-spot awareness, wheel stoppersHi-vis, alarms, lights
Service strikesDBYD, potholing, locatorsInsulated tools, vacuum excavation
Vibration / noiseDistance from pile-driving / blastingHPDs, mufflers
Manual tasksMechanical plant > hand-dig where possibleRotation, ergonomic tool use

11. Records

  • DBYD request and results — kept ≥ duration of excavation; 2 yrs if notifiable incident.
  • Soil-classification report by competent person.
  • Daily / pre-start inspection log — soil, shoring, water, adjacent structure status.
  • SWMS (all revisions) + competent-person design certifications (shoring, batter angles, hydraulic capacity).
  • Incident / near-miss records.

12. Common pitfalls / quick wins

Do

  • Treat "hard compact" with the most suspicion — it fails suddenly and looks fine until it doesn't.
  • Get a geotechnical report for any trench > 1.5 m. It's HRCW; the report justifies your shoring choice.
  • Pothole before plant work. DBYD lists are not exact.
  • Designed shoring first, then permit plant loads — never the reverse.
  • Keep the spoil pile ≥ 1 m back; drain water away from the face.
  • Have a written rescue plan before any worker enters; collapse rescue is a specialised confined-space operation.
  • Provide secured ladders within 7.5 m of every worker.

Don't

  • Skip the geotechnical or DBYD step "to save time".
  • Assume natural slope = safe cut face.
  • Allow a truck or excavator to swing within the unverified zone of influence.
  • Run combustion plant inside an occupied deep trench.
  • Resume work after rain / vibration without re-inspecting the face and shoring.
  • Rely on a trench shield to fix face instability — shields protect occupants, not the face itself.

13. Cross-references

  • See also: [[general_construction_work]], [[demolition_work]]
  • Confined space (deep trenches): [[confined_spaces]] (Phase 3)
  • Plant operating near edge: [[managing_risks_of_plant]] (Phase 3)
  • Foundations: [[risk_management_process]], [[whs_consultation_cooperation_coordination]]
  • Glossary: [[glossary_and_key_concepts]]

Source: excavation_work.md (Safe Work Australia, model Code of Practice, CC-BY-NC 4.0). Edition: October 2018. Last verified against SWA: 2026-04-27.